Project case study · Palm Desert

Commercial Salon Tenant Improvement Electrical in Palm Desert

A full electrical build-out for The Beauty Bar on El Paseo. New lighting, lighting controls and power, wired to commercial standards, passed at every inspection, and set up so the next tenant isn't starting from scratch.

Location
El Paseo, Palm Desert
Project type
Commercial tenant improvement (salon)
Timeline
About 4 months, full build-out
Crew
Grew to 3 electricians mid-project
Inspections
Rough-in, ceiling and final, all passed, plus Title 24 acceptance testing
Contractor
Power On Solutions LLC, licensed C-10 electrical contractor (CSLB #1151468)

Project video Watch the project

Drag to compare Before & after

Glass retail shelves lit on the black feature wall at The Beauty Bar, Palm Desert Glass retail shelves installed on a black feature wall before the lighting was turned on
Glass shelves hung on the black feature wall. Then the shelf lighting on.
LED tape glowing under the marble reception desk at The Beauty Bar on El Paseo Electrician building the LED tape channel for the reception desk on site
LED tape channel built and fit on site. Then glowing under the reception desk.
Finished salon hallway with downlights, cabinets and marble floor, Palm Desert Salon suite at rough-in with walls open, electrical boxes and branch wiring on the studs
Walls open at rough-in, boxes and branch wiring set. Then the finished salon.

Behind the walls Built to commercial standards, and built for the next tenant

For a GC or a landlord, the wiring behind the walls matters as much as the fixtures. Here's what went into this space and why.

  1. EMT conduit main runs overhead in a Palm Desert commercial tenant improvement
    01EMT main runs
  2. Electrical boxes and MC branch wiring set on the existing studs at rough-in
    02Boxes set on the studs
  3. MC cable branch drops landing in a grounded metal junction box
    03MC branch drops
  4. Electrical panel at rough-in with EMT conduit stubs
    04Panel rough-in
  • EMT conduit for the main runs: protects conductors physically, and the next tenant improvement can pull new wire without opening walls or ceilings.
  • MC cable for the branch drops: flexible enough to reach fixtures and devices cleanly, still fully metal-armored.
  • A continuous copper ground, end to end: green equipment ground pulled in every EMT run, every MC branch ground tied into it at grounded metal boxes, so ground continuity doesn't depend on a single fitting.
  • Two fault paths: copper ground plus metal raceway give fault current a low-resistance route back to the panel, so a breaker trips fast and stays safe even if one path is damaged later.
  • Inspection-ready at every stage: passed rough-in, ceiling and final inspections, plus Title 24 lighting compliance and acceptance testing.

Scope of work What we did

  • Supplied and installed all downlights and all lighting controls.
  • Installed the owner-furnished pendants, the reception chandelier and a 16-ft continuous track run with 8 lighting fixtures.
  • Installed LED tape lighting at the front desk.
  • Hallway: Lutron 0-10V dimming, two ceiling occupancy sensors and a Pico remote.
  • Restroom: ceiling occupancy sensor plus a Pico, controlling the lights and the exhaust fan.
  • Wired the space in EMT for the main runs and MC for the branch drops, with a continuous copper equipment ground.
  • Completed the Title 24 lighting Certificate of Installation (NRCI-LTI-E) and passed acceptance testing.

How we work The challenge

Mid-build, the restroom door swing changed in the field. The wall-mounted occupancy sensor we'd planned ended up hidden behind the open door, where it couldn't see anyone. We moved the sensor to the ceiling, kept a Pico on the wall so lights and the exhaust fan can still be controlled by hand, and the room passed acceptance testing.

  1. 01Spot it

    New door swing blocks the wall sensor.

  2. 02Move it

    Sensor relocated to the ceiling.

  3. 03Control it

    Pico runs lights and exhaust fan.

  4. 04Test it

    Passed Title 24 acceptance testing.

Finished work The result

About four months from a gutted shell to open doors on El Paseo. Electrical was coordinated around framing, drywall, ceilings, tile and millwork, the crew grew to three mid-project, and the space passed rough-in, ceiling and final inspections plus Title 24 acceptance testing.

Palm Desert and beyond More projects.

All projects
Finished great room and kitchen with recessed lighting and island chandelier Next project Remodel electrical — Palm Desert Kitchen, Living Room & Master Bath Remodel

Get started Planning a tenant improvement in the Coachella Valley?

Licensed C-10 contractor. Send us your plans or set up a walkthrough and we'll get you a bid.